Project Location: Various streets throughout Hanover Park
Phase: Construction
Project Status: Bids Received
Bid Opening Date: April 6, 2023 at 11:05 AM
Mandatory Pre Bid Meeting: No
Construction Start Date: 2023
Construction Completion Date: August 2023 
Contractor: Corrective Asphalt Materials, LLC
Construction Engineer: In-House
Design Engineer: In-House 
Awarded Construction Amount: $69,000.00
Adjusted Final Construction Amount: $66,102.90 
Funding Source(s): Local