Project Location: | Devon Ave. from the West Village limits to Ontarioville Rd. Ontarioville Rd. from Devon Ave. to Lake St.
|
Phase: | Construction |
Project Status: | Under Construction |
Bid Opening Date: | August 5, 2022 at 12:00 PM |
Mandatory Pre Bid Meeting: | No |
Construction Start Date | Spring 2023 |
Construction Completion Date: | June 1, 2023 |
Contractor: | J. A. Johnson Paving Company |
Construction Engineer: | HR Green |
Design Engineer: | In-House |
Awarded Construction Amount: | $527,500.00 |
Adjusted Final Construction Amount : | TBD |
Funding Source(s): | COVID Relief Funds |
ifer Chandler says:OB
OBJECTIVE:
To improve the condition of the roadway by means of resurfacing the asphalt pavement.
DESCRIPTION:
This project includes the mill and overlay of the specified sections Devon Ave. and Ontarioville Rd. pavements. It also includes spot curb and gutter repairs, any necessary road subgrade patching, underground structure improvements/adjustments, curb ramp improvements to comply with current ADA requirements, and all necessary restoration work.